PublishedApril 19, 2023
Future of CMP power line corridor now rests in jury’s hands
Closing arguments in a civil trial focused on whether developers of the stalled 145-mile line sped up construction simply to gain legal rights to continue building.
-
PublishedApril 18, 2023
Defense rests on day 6 of trial over fate of CMP corridor
Jurors heard more conflicting accounts of why construction work sped up on the electricity line, which is supported by Central Maine Power and would extend 145 miles through western parts of the state.
-
PublishedApril 14, 2023
After 5 days of trial over CMP corridor, many questions remain
In a week of proceedings, the trial over the fate of the Central Maine Power-backed corridor has often involved debate around the type of construction work performed.
-
PublishedApril 14, 2023
Soured on solar? Costs, technical delays dampen outlook in Maine
Community solar farms, which sprouted after a 2019 law went into effect, now face challenges including higher costs for Mainers and glitches in hooking up to the grid.
-
PublishedApril 13, 2023
On day 4 of CMP corridor trial, jurors hear details of project timing
A civil trial could determine the fate of the stalled New England Clean Energy Connect power line project, and Thursday's testimony focused on tasks such as clearing trees and installing poles.
-
PublishedApril 12, 2023
On third day, CMP corridor trial zeroes in on construction timing
The fate of the New England Clean Energy Connect project could hinge on when work began along the 145-mile corridor through western Maine – and why.
-
PublishedApril 11, 2023
Power line construction moved ahead on good-faith schedule, jurors told
New England Clean Energy Connect, backed by Central Maine Power and its affiliates, was repeatedly forced to change timeframes, lawyers for the project said on the second day of a civil trial.
-
PublishedApril 10, 2023
Long-awaited trial over future of CMP electricity corridor gets underway
Five years in the making, the trial that could determine the fate of the 145-mile electricity transmission corridor is expected to last 7 days in state Business and Consumer Court.
-
PublishedApril 4, 2023
State panel urged to hold down rate increase for CMP
A public hearing in Lewiston Tuesday drew a handful of people worried about utility bills
-
PublishedMarch 21, 2023
CMP warns customers to be careful after wave of scam calls
Scam callers have been trying to dupe electricity customers in Maine and elsewhere by threatening to turn off their service.